On Track Update: August 17, 2020

Share

The journey to the I-69 Finish Line started in Martinsville last year with the corridor transforming before our eyes. Beams were set last week on another new bridge being built over S.R. 37. Click here to see photos from the bridge beam installation near Egbert Road and click here to hear from one of the crew members helping to install the beams.

There are ten beams that will support the deck of the bridge. Each of the beams is 140 feet long, longer than any other beams used on I-69 Finish Line. Many bridges are at a 90-degree angle and perpendicular to the roadway. The Egbert Road bridge is at a skew to connect with Old S.R. 37, requiring longer beams to bridge the angle of the roadway. Next steps will include building a metal deck, adding reinforcing steel and pouring the concrete deck. Beams are expected to be installed at the new Perry Road bridge late this month.

The new bridges near Egbert Road, Henderson Ford Road, Perry Road and Waverly Road will provide local connections when I-69 opens in northeast Morgan County. They’ll also help safely carry traffic during next year’s closure of a portion of S.R. 37. The new bridges are expected to open to traffic by late fall. I-69 Finish Line is upgrading State Road 37 to interstate standards from Martinsville to Indianapolis. Watch this short video to learn more about the transformational project.

  • Crews hope to fully reopen the intersection at Egbert Road and Centennial Road later this week. The temporary closure had to be extended because of poor soil conditions in the area leading to additional work. Emergency work allowed for the intersection to reopen to local traffic only this weekend. Detour signage remains, but local traffic can travel very slowly through the intersection. Drivers using detour routes should slow down and drive with caution.
  • A temporary driveway connection for Perry Lane could open later this week. Perry Road access south of Perry Lane is detoured to New Harmony Road, Cragen Road and then to S.R. 37.
  • A new access road is expected to open next month to connect Country Club Drive and Myra Lane along the west side of S.R. 37. Country Club Road access to S.R. 37 has closed permanently. A map shows the detour route for local traffic.
  • Crews have rebuilt the Morton Avenue entrance to the Martinsville Plaza. The improved entrance opened late last week.
  • Pipe and utility work underneath Hacker Drive near S.R. 39 is nearing completion and paving is expected later this week. Some flagging operations will continue in the area for shoulder work.
  • York Street is expected to close at S.R. 39 this week. The closure is for the next phase of construction on S.R. 39. The closure is expected to last a few weeks.
  • Rolling closures and lane closures are possible daily along S.R. 37 near Egbert Road, Henderson Ford Road, Perry Road, Waverly Road and Whiteland Road.
  • Closures with flagging are expected Wednesday — Friday on Ohio Street at Bill Boulevard (at Walgreens) for sewer line improvements.
  • A partial closure of Morgan Street at S.R. 39 is expected late this month. The westbound Morgan Street turn lane onto S.R. 39 northbound will remain open. All other turn movements will be closed for about one week so Morgan Street can be realigned with the widened S.R. 39.
  • The east approach of Whiteland Road at S.R. 37 is expected to close in September. This will be a permanent closure. Watch for more details here in the coming weeks.
  • The I-69 Finish Line project office remains closed temporarily, but our Project Team stands ready to assist. Call 855-INDOT-4U or email INDOT@indot.in.gov to connect with our team. Find the latest news, information and traffic updates at I-69FinishLine.com, Facebook, Twitter and Instagram.

Reminder: The project office is closed temporarily, but you can call or email with any questions, 855-INDOT-4U and INDOT@indot.in.gov.

About I-69 Finish Line
I-69 Finish Line is the sixth and final section of the Interstate 69 connection between Evansville and Indianapolis. The project will upgrade the existing State Road 37 to interstate standards between Martinsville and Indianapolis.Governor Eric Holcomb’s Next Level Connections program fully funded the $1.5 billion project and accelerated construction by three years. I-69 Finish Line is expected to open to traffic in late 2024, improving safety and reducing travel time.

Follow I-69 Finish Line on FacebookTwitter and Instagram.

Customer Service:
1-855-463-6848
www.indot4u.com
indot@indot.IN.gov

Media Contact:
Natalie Garrett
Office: 812-524-3733
Cell: 812-525-0571
nagarrett@indot.in.gov

Categories

The Latest Updates